Market prices.

Published rates and benchmarks for hemp blocks, waffle slabs, void formers and Durra Panel, with material-only arithmetic for the reference building.

Status: published rates and benchmarks, collected to start preliminary cost modelling. Every source on this page was found by our research partner. We could not open them and have not read them, so each figure is reported by research partner, not read by us. The arithmetic is ours and has been checked. Nothing here is a quotation for our reference building, and no actual project quotation has been obtained yet.

What kind of number is this?

TypeMeaningExamples on this page
Published supplier priceA price a supplier shows publicly, usually indicative, with stated inclusionsHemp block rates, Durra Panel from $39.10/m²
Quantity surveyor benchmarkA rate published by a cost consultant, for a stated place and scopeMelbourne waffle slab rates
Manufacturer claimA statement by the maker that we have not independently verifiedClaimed R values, Durra comparison
Calculated estimateOur arithmetic on the above and on our takeoffMaterial-only wall costs, 174 m² slab scenarios
Actual project quotationA written quote for our reference buildingNone yet

All prices are per m² and exclude GST unless stated. They are material costs or part-installed rates in other regions or states, mostly before transport to a South East Queensland site.

1. Published hemp block prices

Three suppliers are reported to publish indicative prices. Inclusions differ, so the rates are not like for like. KOSP (IsoHemp) prices are based on container quantities and include blocks, adhesive or mortar and delivery to an Australian capital-city port, but not onward transport. RespiraBuilt (RespiraBlock) prices include mortar and exclude freight from Melbourne, and its R values are manufacturer claims that need supporting technical documentation. HempBLOCK prices include estimated shipping and exclude transport to site, with minimum orders. Sources: KOSP, RespiraBuilt, HempBLOCK pricing page.

Calculated estimate The table applies each rate to the Mallee net external wall area from our takeoff (95.2 m², range 85.7 to 104.7 m²). We do not know whether suppliers price on net or gross wall area, so the last column shows the gross area (141.2 m²) as an upper bound. These are material-only figures. They are not complete installed wall costs.

Supplier and productThicknessPublished rate per m² (ex GST)Claimed R valueMaterial-only, net wall 95.2 m²Range, net wall 85.7 to 104.7 m²If rate applied to gross wall 141.2 m²
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port75 mm$90$8,568$7,713 to $9,423$12,708
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port90 mm$98$9,330$8,399 to $10,261$13,838
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port120 mm$125$11,900$10,712 to $13,088$17,650
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port150 mm$160$15,232$13,712 to $16,752$22,592
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port200 mm$195$18,564$16,712 to $20,416$27,534
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port250 mm$240$22,848$20,568 to $25,128$33,888
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port300 mm$280$26,656$23,996 to $29,316$39,536
KOSP IsoHemp: Hemp block, blocks, adhesive or mortar, delivered to a capital-city port360 mm$365$34,748$31,280 to $38,216$51,538
RespiraBuilt RespiraBlock: Block with mortar, ex Melbourne80 mm$114R1.84$10,853$9,770 to $11,936$16,097
RespiraBuilt RespiraBlock: Block with mortar, ex Melbourne120 mm$164R2.67$15,613$14,055 to $17,171$23,157
RespiraBuilt RespiraBlock: Block with mortar, ex Melbourne200 mm$245R4.34$23,324$20,996 to $25,652$34,594
RespiraBuilt RespiraBlock: Block with mortar, ex Melbourne300 mm$335R6.42$31,892$28,710 to $35,074$47,302
HempBLOCK: LB300 interlocking blocks300 mm$265$25,228$22,710 to $27,746$37,418
HempBLOCK: LB300 blocks and render to both sides300 mm$330$31,416$28,281 to $34,551$46,596
HempBLOCK: Veneer blocks, mortar and render one side100 mm$151$14,375$12,941 to $15,810$21,321
HempBLOCK: Veneer blocks, mortar and render one side150 mm$186$17,707$15,940 to $19,474$26,263
HempBLOCK: Veneer blocks, mortar and render one side200 mm$267$25,418$22,882 to $27,955$37,700
HempBLOCK: Veneer blocks, mortar and render one side300 mm$270$25,704$23,139 to $28,269$38,124
HempBLOCK: Veneer blocks, mortar and render both sides300 mm$302$28,750$25,881 to $31,619$42,642

What the numbers suggest, and what they do not

  • Price per m² rises with thickness, but not in proportion. KOSP per 100 mm of block: 75 mm $120, 120 mm $104, 300 mm $93, 360 mm $101.
  • At 300 mm the published rates range from $265 (HempBLOCK LB300, blocks only) to $335 (RespiraBlock, with mortar). HempBLOCK’s render adds about $32 a side ($302 less $270 for veneer, and $330 less $265 for LB300). so the rates are not directly comparable.
  • One HempBLOCK row looks inconsistent: 200 mm veneer at $267 is only $3 below 300 mm at $270, while 100 mm and 150 mm are $151 and $186. The 200 mm figure may be a typing error. We will ask.
  • These rates are in the same region as the historical ABC figures ($100 to $150/m² for blocks, Will Brain, 2024), and thin blocks in KOSP’s range overlap with them. That is consistent, not proof that the products or inclusions are equivalent.
  • The most economical hemp system may not use the thickest block everywhere. A thinner block needs a frame and insulation to reach the same performance, and we do not yet know those costs.

Not yet in the numbers

Onward transport to site, structural framing or the steel and concrete frame, insulation where blocks are thin, fixings, render or other finishes where not included, weatherproofing, internal linings, labour (the hemp labour rates on the HempBLOCK page are ambiguous, so we are not using them), equipment, waste, and compliance documentation. Our conventional comparison walls (timber frame with brick veneer, and timber frame with lightweight cladding) have no sourced rates yet.

Wall thickness changes the floor area

With the internal dimensions held, each additional 100 mm of external wall thickness adds about 5.2 m² to the footprint (conditioned perimeter 52.3 m × 0.1 m, ignoring corners). Held to the footprint, it removes the same amount of usable internal area. A 300 mm wall against a 100 mm wall is about 10.5 m². We have not costed this. It affects slab, roof and land use, and should be counted in the comparison.

HempBLOCK: is this the product in our profile?

The pricing page is on hempblockaustralia.com and refers to HempBLOCK International. Our HempBLOCK profile draws on au.hempblockinternational.com and describes HempBLOCK Australia selling blocks made in Europe under licence. LB300 appears in both. Whether they are the same entity and product range is not established, so the certification caveats in the profile stand: the historical CodeMark certificate is not confirmed as current, and nothing here implies compliance.

2. Waffle slab cost benchmark

A March 2026 article by Coba Pekaj, MAIQS CQS, of Pekaj Group, reports Melbourne supply-and-install rates including pods, reinforcement, concrete, labour and pump hire, excluding site preparation, earthworks, piling and ground improvement, and GST. Source: Pekaj Group.

Slab sizeMelbourne supply-and-install benchmark (ex GST)
Under 120 m²$110 to $160/m²
120 to 200 m²$95 to $135/m²
Over 200 m²$90 to $125/m²

Calculated estimate Applying the 120 to 200 m² range to the stated 174 m² footprint (house and garage):

174 m² scenarioRateCalculated total (ex GST)
Low$95/m²$16,530
Central$115/m² (midpoint)$20,010
High$135/m²$23,490

The arithmetic checks ($95, $115 and $135 times 174). These are Melbourne benchmark scenarios, not Queensland quotations, and they exclude earthworks and site preparation.

Reconciliation needed. The article is also reported to include a worked example of a 246 m² slab costing $43,319. That is about $176/m², which is 41% above the top of the over-200 m² range ($125) and would be $12,569 more than $125 would give. The example may include items outside the headline rate, such as earthworks, edge beams or extras, but we have not read it. Until we reconcile the two, we rely on neither. Our preliminary foundation model will carry both a benchmark case and a worked-example case.

3. Void former prices: EPS and alternatives

A feasibility study hosted by Sustainable Foundations Group is reported to give average void former material prices, excluding GST and freight. Source: feasibility study (PDF).

Void former (reported averages, ex GST and freight)Per m²If it covers up to 174 m²
Conventional EPS pods$13.06$2,272
Alternative products$24.08$4,190
Difference$11.02 (84% higher)$1,917

We assumed, for scale only, that void formers cover up to the whole 174 m². In practice ribs and edge beams take area, so the real quantity is less. The gap is under $2,000 on that basis. The central question is whether higher void former costs are offset by savings in concrete, reinforcement, labour or time.

Not yet established: original publication date (the upload path suggests May 2025), authors and commissioning organisation, products compared, supplier quotations, concrete and reinforcement quantities, labour and installation costs, environmental findings, limitations, and whether the “alternative products” include BIAX. We do not assume it reflects current prices.

4. Durra Panel pricing and partition quantities

The manufacturer’s FAQ page is reported to state: natural-finish panels start at $39.10/m²; made in Bendigo, Victoria; standard panel width 1,187 mm; nominal thicknesses 50 mm and 58 mm; manufactured to order; Australian distribution available. GST treatment and delivered project pricing are unconfirmed. Source: Durra Panel FAQs. See the profile.

Which area is 144 m²?

Our 144 m² is the single-face wall area: partition length 53.2 m times 2.7 m, with each wall counted once. The lining surface on both faces of those walls is about 287 m². A Durra partition is a solid panel, so the panel quantity is the wall area, not both faces. What the manufacturer’s $/m² rates are per (wall area or face area) is not stated, which affects every cost comparison. We will ask.

Laying out around the 1,187 mm panel width

Panel lengths are made to order, so height is flexible. Width is the constraint. Partition runs that match whole panel widths avoid cutting. Joints and door openings are ignored here.

Partition runLengthPanel widths neededWhole panelsWidth suppliedOverage if uncutLengths that need no cutting
Laundry|study and study|kitchen dividers (2 walls)4.2 m3.504 per wall4.75 m14%3.56 m or 4.75 m
Corridor wall, south side17.1 m14.4115 per wall17.80 m4%16.62 m or 17.80 m
Corridor wall, north side9.3 m7.838 per wall9.50 m2%8.31 m or 9.50 m
Bedroom and wet-area dividers (5 walls)3.7 m3.124 per wall4.75 m28%3.56 m or 4.75 m

Whole panels for the listed runs come to 51, against 44.8 panel widths of actual wall. Cut panels can use offcuts elsewhere, so the real quantity lies between those figures.

Panel quantity basis (2.7 m high)Panel areaAt $39.10/m² (ex GST, material only)
Wall area, no waste (53.2 m × 2.7 m)143.7 m²$5,618
Whole panels, 51 panels, no cutting reuse163.4 m²$6,391
Both faces (for comparison only; not the panel quantity)287.4 m²$11,237

Calculated estimate This is a panel-only figure. It leaves out delivery, fixings, door framing, finishes and labour. The manufacturer’s comparison reports $77.67/m² installed, so about $38.57/m² sits above the panel price if the two figures are on the same basis, which is unconfirmed.

5. Hemp panel manufacturing: a research strand

The Australian Hemp Council’s document Hempcrete Modular Panels: Industry Insights and Future Action for Affordable Carbon Housing (July 2025) was found by our research partner. Source: PDF. We have not read it. It is reported to estimate about 14 tonnes of hemp hurd per house, from about 0.7 to 2 hectares of crop.

A check we can already make: 14 tonnes from 0.7 to 2 hectares implies a hurd yield of 7 to 20 tonnes a hectare. That looks high against our general understanding of typical hemp stem yields, so the document’s assumptions need verifying before we publish any figure as a finding. For scale, the ABC article says the Preston house (about 400 m², cast in place) used about 10,000 kg of hemp, and that article does not say how that compares with a house of our size.

Topics to investigate once we can read it: Australian production and processing, agricultural supply chains, regional manufacturing, prefabricated panels, manufacturing economics, housing affordability, carbon impacts and commercial scalability. This could become its own strand linking agriculture, manufacturing and housing.