Homes & Materials · Research collection
The Circular Home
Rethinking how we build. Can we build better, more sustainable, more comfortable and more affordable homes, faster, using technologies and materials that are already available?
An open investigation, started on 15 November 2026. Most of the questions below are still unanswered, and that is part of the point. Nothing here is a design, a quotation or advice.

Why this research
Housing is under pressure from several directions at once: rising construction costs, affordability, labour shortages, slow construction programmes, material waste, higher insurance and maintenance costs, environmental impacts and fragmented supply chains.
Most sustainable building research looks at one product at a time. This collection asks how products, construction systems and design choices could work together, and whether sustainable housing can become the obvious economic choice instead of a premium one. We do not yet know the answer.
How we investigate
This is not an attempt to prove a conclusion. We do not assume that:
- sustainable materials are automatically better for the environment;
- innovative products are automatically cheaper;
- prefabrication is always faster or more economical;
- conventional construction is inherently inefficient;
- natural materials always beat manufactured ones;
- manufacturer claims reflect real-world performance.
Where conventional construction performs better, we will say so. Where information is missing, we will say what is unknown. Unknown is a useful research result.
Every finding carries a label, so you can see how much weight it deserves: verified evidence, academic research, manufacturer information, calculated result, hypothetical scenario or research target. See how Circular Abundance labels evidence. We publish as we go: Publish. Learn. Improve. Repeat.
The reference building
To compare construction systems fairly, every scenario needs the same house: the same floor area, rooms, openings, performance requirement, site and finish quality. We plan to use a simple single-storey home of about 150 m² as the reference, and later test whether redesigning the building around a construction system saves more.
The reference is Mallee House (Brisbane), one of the free Design For Place designs published by the Australian Government on YourHome. We have read its Design Options document and its technical drawing package (11 preliminary drawings, issued June 2023).
Confirmed from those documents: single storey, three bedrooms, two bathrooms, a study nook and a single garage; 148 m² of enclosed living area, 26 m² garage and 174 m² gross floor area; 30 m² of decks; and a Brisbane design pack. Three variations are modelled at 8.5, 9.2 and 10 stars, with Whole of Home scores of 69, 95 and 101. The wider Design For Place programme aims at a minimum 7 star NatHERS rating and 60/100 Whole of Home (the minimum for NCC 2022 compliance).
Still to confirm: the climate zone and north-facing rear orientation reported to us (we did not find the climate zone in the two documents we hold), and any engineering (the 100 mm slab figure does not establish the footing design). The drawings are preliminary guides, not certified documentation, and give no footing, beam or reinforcement details. Our reference building page sets out the specification and a preliminary quantity takeoff, with the source, method and status of every figure. We link to the official documents, and show one cropped floor plan with the required attribution.
Design For Place is © Commonwealth of Australia 2026, licensed under CC BY 4.0, and provided free of charge at www.yourhome.gov.au. Our quantities and commentary are our own work, not produced or endorsed by the Commonwealth.
Five construction scenarios
Each scenario will be described, quantified and costed against the same reference building. Only the conventional baseline and one scenario, Durra Panel partitions, have been costed so far, and only from published benchmarks and our own assumptions (see the baseline and the Durra Panel partition comparison).
A. Conventional Australian construction
A realistic South East Queensland benchmark based on what builders are building now: concrete slab, timber or light steel framing, brick veneer or conventional cladding, bulk insulation, plasterboard and standard finishes. We will check current practice rather than rely on an old specification.
B. Optimised conventional construction
Improvements that fit into a normal building process: BIAX Foundations, lower-carbon concrete, optimised framing, Durra Panel, efficient cladding, better insulation and standardised dimensions.
C. Bio-based construction
Renewable and agricultural materials, including HempBLOCK, other hemp block systems, cast-in-place hempcrete, prefabricated hemp panels, engineered timber, cellulose or wood fibre insulation and straw-based systems. We will assess complete compliant assemblies, not products in isolation.
D. Prefabricated and panelised construction
Open and closed timber panels, structural insulated panels, factory-fitted insulation and windows, floor and roof cassettes, and modular or flat-pack systems. A key question is whether panels strike a better balance than fully modular homes between factory efficiency, transport cost and on-site flexibility.
E. The optimised Circular Home
A home designed around the best findings, not a conventional house with materials swapped in. That means standard manufacturing dimensions, efficient spans, simple roofs, fewer trades, concentrated plumbing, passive solar design, and a building that can be repaired, adapted and eventually taken apart.
What we will measure
- Cost: hard construction cost and complete project delivery cost, kept separate, with every inclusion and exclusion stated (land, site works, fees, approvals, connections, contingency, margin, finance, solar and battery, GST).
- Time: factory time, on-site time and total delivery time, the critical path, and what a shorter programme is worth.
- Whole of life: over a stated 30 or 50 year period, energy, maintenance, replacement, durability, moisture risk, insurance, embodied and operational carbon, and end-of-life recovery.
- Design: whether simpler design can remove cost before any material is substituted. This may turn out to be the most important finding.
Where one system combines functions (a wall panel that provides structure, insulation and lining, for example) we will compare complete installed assemblies of equal performance and avoid counting savings twice.
Research updates
16 November 2026 (update 007): status
The Circular Home continues as an ongoing flagship research project, and we have broadened our focus across Circular Abundance. Detailed construction cost modelling is paused until supplier quotations or measured productivity are available. Everything published here remains preliminary.
16 November 2026 (update 006): Durra Panel partitions and baseline refinements
We published a preliminary comparison of Durra Panel and timber-framed plasterboard partitions, comparing complete installed assemblies, labour and the construction programme. On our assumptions Durra is dearer in the central case and the break-even panel price is well below the reported price, but almost every rate is our own assumption and no supplier has quoted. Ceilings are investigated separately and not costed. We also refined the baseline: preliminaries and markup, site works, the inspection sequence, curing against readiness for loading, source labelling and a separate 8.5-star specification.
16 November 2026 (update 005): conventional cost and programme baseline
We published a preliminary cost and programme baseline for building the Mallee reference home conventionally in South East Queensland: an elemental cost model with low, central and high estimates, cost per square metre on three floor area bases, a trade programme with inspections and labour, ten ranked opportunities and a list of questions for quotation. It rests on published benchmarks, not quotations, and says which figures are our own assumptions. It is the yardstick the better-materials scenarios will be tested against.
15 November 2026 (update 004): market prices
We added a market prices page: published hemp block rates from three suppliers, a Melbourne waffle slab benchmark, void former prices and Durra Panel pricing, with material-only arithmetic for our reference building. Our research partner found all of these sources and we have not read them, so each is labelled that way. Two things need reconciling first: a worked waffle slab example about 41% above the benchmark range, and what the Durra and hemp rates are per. Supplier enquiries are drafted for review and have not been sent.
15 November 2026 (update 003): slab clarified, foundations and assemblies opened
The 100 mm slab in the Mallee documents is not inherently non-compliant. It appears to define the slab panel for energy modelling, and the footing design is unknown. We have opened a foundation comparison (stiffened raft, EPS waffle pod, BIAX, screw piles, starting with a hypothetical Class S site), extended the takeoff to rooms, partitions, linings, ceilings, doors and wet areas with low, central and high ranges, and begun assembly comparisons. No supplier prices have been obtained yet.
15 November 2026 (update 002): reference building confirmed, takeoff begun
Mallee House (Brisbane) is now confirmed from the official documents, and we have started a preliminary quantity takeoff. Our research partner reports that the Queensland cost report puts the average adjusted hard construction cost of a 235 m² detached Brisbane house at $455,509 excluding GST (about $1,938 per m²). A manufacturer comparison for Durra Panel and a literature review on prefabrication have also been reported. We have not read those three sources ourselves, so the early findings page labels them accordingly. We have also published a supplier quotation schedule.
15 November 2026 (later): hemp cost source read
We read the ABC article behind the reported hemp cost ranges. The figures are real but come from one hemp builder, and what they cover is not stated. Details are on the early findings page.
15 November 2026: collection started
We opened the collection and checked the first sources. Some held up and some could not be confirmed. The results, with sources and limits, are on the early findings page, together with a hypothetical cost framework and the outstanding questions.
Related
- Early findings, cost framework and outstanding questions
- Reference building and preliminary takeoff
- Conventional cost and programme baseline
- Durra Panel partitions against timber and plasterboard
- Market prices
- Foundation comparison
- Assembly comparisons
- Supplier quotation schedule
- The Research Notebook, for questions still being worked on
- Homes & Materials product research profiles