The Circular Home · Research assignment 01 · Preliminary
What would a conventional build cost, and how long would it take?
A baseline for the Mallee reference home in South East Queensland, built from published benchmarks with every assumption in view. It is the yardstick we will test better materials and methods against.
The short version
For a conventional 174 m² build (house and garage), published benchmarks point to a contract price of about $365,000 excluding GST ($2,100 per m² of gross floor area), within a range of $313,000 to $461,000. On the living area alone (148 m²) the central figure is $2,469 per m². An indicative efficient programme, not a verified industry average, runs about 19 weeks on site (11 to 33 in our range), before design, approvals and delays outside the site.
The three largest cost groups are kitchen, bathrooms and finishes ($56,700), internal walls and ceilings ($48,400), plumbing, electrical and air conditioning ($41,200). Finishing work (internal linings, kitchen, bathrooms and floor finishes) is the largest pool for cost and time savings, at about $105,000.
How far to trust this. No builder or quantity surveyor has priced these drawings. The total rests on published benchmarks. The split into elements is an allocation of that total using one builder’s Melbourne example, so the elements are not independent measurements. About 69% of the central total rests on published benchmarks and 31% on our own assumed splits. None rests on a verified price or a manufacturer claim. We publish it now so it can be corrected, and we will replace each assumption as quotations arrive.
1. What the numbers cover
Reference building. The Mallee House (Brisbane), a free Australian Government design: single storey, three bedrooms, two bathrooms and a study nook. The drawings state 148 m² of living area and a 26 m² garage, so a gross floor area of 174 m², plus 30 m² of decks under pergolas. Our preliminary takeoff holds the quantities.
Floor area basis. Published rates are not always clear about the area they use, so we state cost per m² on three bases: living area only, gross floor area of 174 m² (our main basis, matching the garage-inclusive area on the drawings) and 204 m² if covered decks are counted, as some quantity surveyors do.
Price basis. Australian dollars, excluding GST, mid-2026 prices, South East Queensland, standard-to-medium inclusions, a builder's contract price (trade costs, preliminaries, overheads, margin).
Markup, not gross margin. The 20% from Pekaj Group is a markup on trade cost. As a share of the contract price it is 16.7%. We use “markup” for the 20% and avoid calling it a gross margin.
Not included:
- Land
- Design, engineering and certification fees
- Council and authority charges and service connection fees
- Landscaping, driveways and fencing
- Site-specific extras (flood, bushfire, steep slope, rock, reactive clay beyond Class M)
- Finance
- GST
- Escalation after mid-2026
Published figures give a sense of scale for several of these: site works provisional sums of $10,000 to $30,000 and service connections of $5,000 to $25,000 (S1); soil test, slab engineering and termite barrier of about $3,300 to $9,000 (S5); landscaping of $15,000 to $50,000 (S1); professional fees, permits and authority charges of $60,000 to $170,000 or more in one Melbourne guide (S4); and a variations allowance of 5 to 10% of contract value (S2).
2. Cost per square metre
| Floor area basis | Low (ex GST) | Central (ex GST) | High (ex GST) | Central (inc GST) |
|---|---|---|---|---|
| Living area only (148 m²) | $2,116 | $2,469 | $3,116 | $2,716 |
| Gross floor area, house and garage (main basis) (174 m²) | $1,800 | $2,100 | $2,650 | $2,310 |
| GFA plus 30 m² of pergola decks (204 m²) | $1,535 | $1,791 | $2,260 | $1,970 |
These totals are anchored on published ranges, not built up from quantities. The low case is the AIQS Building Cost Index “standard house” rate for March 2026 as quoted by Pekaj Group ($1,800 per m², ex GST, including profit and preliminaries). The central case is its “medium standard house” rate ($2,100). The high case is the midpoint of a Brisbane mid-market builder range ($2,300 to $3,000, GST basis not stated). We have not applied escalation. Rider Levett Bucknall forecasts Brisbane tender prices up 5.0% in 2026 and 7.0% a year from 2027, but that is a commercial index, not a house index (S7).
What other published sources say
| Source | Per m² | GST | What it covers | Ref |
|---|---|---|---|---|
| Newstart Homes, Brisbane suburbs, base builder (1 Oct 2026) | $1,500 to $1,800 | Not stated | Construction only, Homemaker inclusions; site costs, land and approvals excluded | S1 |
| Propertylens, Brisbane volume builder, standard inclusions (early 2026) | $1,800 to $2,200 | Not stated | Build contract; knockdown, flood, landscaping extra | S2 |
| Propertylens, Brisbane mid-market builder (early 2026) | $2,300 to $3,000 | Not stated | Better inclusions | S2 |
| OJ Pippin, Brisbane (13 Feb 2026) | $1,900 to $5,000 | Not stated | Standard new build; the article's introduction says $5,500, its body $5,000 | S3 |
| Pekaj Group, single storey house, Melbourne (4 Apr 2026) | $2,376 | Includes 20% margin and 10% GST ($1,800 trade cost, $2,160 ex GST) | Small and custom builder rates; volume builders reported 20 to 25% lower | S4 |
| AIQS Building Cost Index, March 2026, standard to medium standard house | $1,800 to $2,100 | Ex GST | Includes profit and preliminaries; GFA basis; location not stated (as quoted by Pekaj Group) | S4 |
These sources broadly agree on a zone of about $1,800 to $2,400 per m² for a conventional Brisbane home with standard inclusions, but they differ on GST, floor area, site costs and inclusions, so they cannot be compared tightly. Our earlier hypothetical elemental table ($319,000 for the 174 m² home) sits just above the low case.
3. Elemental cost model
Each element is its share of trade cost (Pekaj Group, S4) applied to the total above. We removed the first floor framing line because the Mallee House has one storey, then rescaled the rest. Margin is the 20% Pekaj publishes as indicative. The model is a data file, so any element can be replaced.
| Element | Share | Low | Central | High | Central per m² GFA | Evidence class |
|---|---|---|---|---|---|---|
| Site preparation and earthworks | 1% | $3,000 | $3,500 | $4,400 | $20 | Published benchmark (allocated) |
| Foundations and slab | 9% | $24,100 | $28,100 | $35,500 | $162 | Published benchmark (allocated) |
| Structural framing | 9% | $23,300 | $27,200 | $34,300 | $156 | Published benchmark (allocated) |
| External walls and cladding | 6% | $15,100 | $17,600 | $22,200 | $101 | Published benchmark (allocated) |
| Roofing | 6% | $15,100 | $17,600 | $22,200 | $101 | Published benchmark (allocated) |
| Windows and external doors | 5% | $13,700 | $16,000 | $20,200 | $92 | Published benchmark (allocated) |
| Insulation | 2% | $6,000 | $7,000 | $8,900 | $40 | Our assumption (split) on a published benchmark |
| Internal walls and ceilings | 16% | $41,500 | $48,400 | $61,100 | $278 | Our assumption (split) on a published benchmark |
| Plumbing, electrical and air conditioning | 14% | $35,300 | $41,200 | $52,000 | $237 | Published benchmark (allocated) |
| Kitchen, bathrooms and finishes | 19% | $48,600 | $56,700 | $71,600 | $326 | Our assumption (split) on a published benchmark |
| External services and works inside the contract | 4% | $11,500 | $13,400 | $16,900 | $77 | Published benchmark (allocated) |
| Builder preliminaries | 9% | $23,800 | $27,800 | $35,100 | $160 | Published benchmark (allocated) |
| Builder overheads, insurance, contingency and margin (20% of trade cost) | $52,200 | $60,900 | $76,800 | $350 | Published benchmark | |
| Total contract price, ex GST | $313,200 | $365,400 | $461,100 | $2,100 | ||
| Total contract price, inc GST | $344,500 | $401,900 | $507,200 | $2,310 |
Rounded to the nearest $100, ex GST. Notes on each element, the shares and the sources are in the model’s data file and CSV in the project repository. Where a split is ours, the evidence class says so.
Are preliminaries counted twice?
The model carries a builder preliminaries element ($27,800 central, Pekaj’s 8.7% share of trade cost) and then adds the 20% markup. Pekaj describes that 20% as covering preliminaries and overhead (6 to 8%), insurance and finance (2 to 3%), contingency and risk (2 to 3%) and net profit (3 to 5%). Site supervision, scaffold and temporary works are direct site costs, while head-office overhead is not, but Pekaj does not draw the line, so some overlap is possible. We keep both in the central case and show what removing an overlap would do:
| Case | Central total, ex GST | Change | Note |
|---|---|---|---|
| Prelims element as modelled (8.7% of trade cost) plus 20% markup | $365,400 | $0 | Both counted |
| If 3.5% of trade cost in the markup is the same cost as preliminaries | $352,600 | -$12,800 | Overlap removed |
| If 7.0% of trade cost in the markup is the same cost as preliminaries | $339,800 | -$25,600 | Overlap removed |
We have not seen a builder’s preliminaries schedule. That is the document that would settle it.
Does the allocation match published unit rates?
For the three elements where we found independent published rates, we compared them with the allocated figures.
| Check | Allocated (low / central / high) | Published range | Result | Basis |
|---|---|---|---|---|
| Slab: published unit rates | $24,100 / $28,100 / $35,500 | $20,400 to $35,100 | Inside the published range | Waffle pod $110 to $170 per m2, stiffened raft $130 to $200 per m2 (incl GST); Brisbane house slab, M class, $115 to $170. We use the waffle pod range, converted to ex GST. Soil test $600 to $1,500, engineering $1,200 to $3,500, termite management $1,500 to $4,000 (S5; GST basis not stated, treated as stated). S5 |
| Roof sheeting: published unit rates | $15,100 / $17,600 / $22,200 | $13,600 to $22,000 | Inside the published range | Colorbond new build in Brisbane $65 to $105 per m2 installed (incl GST), roof area on the slope. Battens, insulation and flashings may be extra. Coastal grade steel adds 10 to 20% to material. S6 |
| Site works: published provisional sums | $3,000 / $3,500 / $4,400 | $10,000 to $35,000 | Below the published range | Newstart (S1): site works provisional sum $10,000 to $30,000 plus service connections $5,000 to $25,000 (excluded here). Propertylens (S2): $35,000 for soil, slope and connections in a worked example. Sydney guide (S13): $40,000 to $90,000 on a moderate slope. S1, S2, S13 |
The slab and roof allocations sit within published unit rates, which supports the method. Site works are the weak point: the allocation is small because Pekaj’s example is a level site, whereas published provisional sums are several times higher. We treat site works as the largest swing item and exclude site-specific extras from the total. If a real site needed the published provisional sums, the central total would move like this:
| Site works | Element cost | Central total, ex GST | Change |
|---|---|---|---|
| Allocated site works in the model | $3,500 | $365,400 | $0 |
| Published provisional sum of $10,000 | $10,000 | $373,200 | +$7,800 |
| Published provisional sum of $20,000 | $20,000 | $385,200 | +$19,800 |
| Published provisional sum of $30,000 | $30,000 | $397,200 | +$31,800 |
Site works are the cheapest allowance in the model and the likeliest to be wrong. A soil test, site survey and earthworks quote for the actual block would replace the allowance.
4. Where the money goes
Finishing is large because it spans many trades: interior linings, floor coverings, tiling, joinery and fittings together come to about $105,000. Structure (slab, framing, roof, cladding and windows) is the other big block. For the external walls, the brick veneer allocation works out at about $185 per m² of net wall, a useful yardstick against reported hemp block rates of $90 to $365 per m² of wall for materials alone (not installed, and not read by us at source; see market prices).
5. Conventional construction programme
This is an indicative efficient programme, not a verified industry average. It covers on-site construction only, from site start to practical completion, and excludes design, approvals, contract and finance. Durations are working days (5 a day week), our assumptions informed by the published stage ranges below, and need a builder's review. Public holidays, the Christmas shutdown and wet weather beyond the allowance are not modelled.
| Task | Trade | Crew | Days (low / central / high) | Central start to finish (working day) |
|---|---|---|---|---|
| Site start: set-out, fencing, erosion control, temporary services Critical path | Builder and labourers | 2 | 2 / 3 / 5 | 0 to 3 |
| Excavation and footings or pod set-down Critical path | Excavator operator and labourers | 3 | 2 / 3 / 5 | 3 to 6 |
| Hold point: certifier inspects excavation and footings Critical path Hold point Queensland inspection sequence is excavation, footings, slab, frame and final (S12). We hold the first two together before steel and under-slab services. Inspector availability is our assumption. | Building certifier | 1 / 1 / 3 | 6 to 7 | |
| Under-slab plumbing and drainage Critical path | Plumber | 2 | 2 / 2 / 4 | 7 to 9 |
| Termite barrier, vapour barrier, reinforcement, pods and formwork Critical path | Concretors and steelfixers | 4 | 3 / 4 / 6 | 9 to 13 |
| Hold point: certifier inspects slab reinforcement and services before the pour Critical path Hold point Third of the five Queensland inspections (S12). A failed or missed inspection stops the pour. | Building certifier | 1 / 2 / 4 | 13 to 15 | |
| Slab pour and finish Critical path | Concretors, pump | 5 | 1 / 1 / 2 | 15 to 16 |
| Slab curing, then confirmation the slab is ready for structural loading Critical path Two different things. Curing is the strength-gain period the engineer specifies. Readiness for loading is when the engineer or builder lets the frame, trusses and roof loads onto the slab, which may be later than minimum curing. We assume seven working days for both and could not verify any figure: the QBCC and WA Building and Energy material we read gives no number of days (S15). | None (waiting) | 5 / 7 / 10 | 16 to 23 | |
| Wall frames, roof trusses and bracing Critical path | Carpenters | 4 | 8 / 12 / 18 | 23 to 35 |
| Roof cover, gutters and flashings | Roof fixers and roof plumber | 3 | 3 / 5 / 8 | 31 to 36 |
| Windows, external doors, wall wrap and cladding (lock-up) | Carpenters, glaziers, cladders | 4 | 6 / 10 / 16 | 32 to 42 |
| Rough-in: plumbing, electrical and air conditioning Critical path | Plumber, electrician, mechanical | 3 | 5 / 8 / 12 | 35 to 43 |
| Hold point: certifier inspects the frame Critical path Hold point | Building certifier | 1 / 2 / 5 | 43 to 45 | |
| Wall and ceiling insulation Critical path | Insulation installers | 2 | 2 / 3 / 5 | 45 to 48 |
| Plasterboard hanging and setting Critical path | Plasterers | 4 | 6 / 10 / 15 | 48 to 58 |
| Wet area waterproofing and membrane cure | Waterproofer | 2 | 3 / 4 / 7 | 56 to 60 |
| Wall and floor tiling | Tilers | 2 | 5 / 8 / 12 | 60 to 68 |
| Kitchen, vanity and robe joinery install Critical path | Cabinet makers, carpenters | 3 | 4 / 6 / 10 | 60 to 66 |
| Internal doors, skirtings and trim Critical path | Carpenters | 2 | 4 / 6 / 10 | 58 to 64 |
| Painting, two coats Critical path | Painters | 3 | 6 / 10 / 15 | 64 to 74 |
| Fit-off: plumbing, electrical, air conditioning, appliances, floor coverings Critical path | Plumber, electrician, floor layers | 4 | 6 / 10 / 16 | 71 to 81 |
| Final clean, defect fixes, certifier final inspection and certificates Critical path Hold point Queensland final stage collects termite, wet area membrane, glazing, smoke alarm and energy certificates (S12). | Builder, certifier | 2 | 3 / 5 / 10 | 81 to 86 |
| Practical completion and handover Critical path | Builder | 2 | 2 / 3 / 5 | 86 to 89 |
Result. The central programme runs 94 working days, about 19 weeks, including a 5 day weather allowance. The low case is 11 weeks and the high case 33. The central critical path runs through 19 tasks, including the slab and its curing, framing, rough-in, linings, joinery, painting and fit-off.
Inspection sequence. Queensland requires a building certifier to inspect a new Class 1a house at five stages: excavation, footings, slab, frame and final (S12). We model them as three hold points: excavation and footings (H0), slab reinforcement and services before the pour (H1), the frame (H2), and a final inspection with certificates (H3). Each is a possible stop to the next trade, and inspector availability is our assumption. The final stage collects termite, wet area membrane, glazing, smoke alarm and energy certificates.
Curing is not the same as readiness for loading. Curing is the strength-gain period the engineer specifies. Readiness for structural loading is when the engineer or builder allows the frame, trusses and roof loads onto the slab, and it may come later than the minimum cure. Our programme has one task for both and assumes seven working days. We could not verify that figure: the QBCC and WA Building and Energy material we read gives no number of days (S15), so the engineer’s specification must settle it.
How this compares with published figures.
- Slab 1 to 3 weeks, frame 2 to 4, lock-up 2 to 5, fixing 4 to 10, plus site preparation 1 to 3 and practical completion 1 to 4: about 11 to 29 weeks if sequential S9.
- Construction phase typically 16 to 24 weeks after design; fixing to completion 4 to 8 weeks S10.
- Volume build 28 to 40 weeks; custom build 40 to 60 weeks S2.
- Project homes around 6 to 12 months; custom 12 to 24 months (building approval or start to completion, not stated) S11.
- National average detached house 11.5 months from building approval to completion in 2024-25 (ABS, via the National Housing Supply and Affordability Council, reported by S9); Productivity Commission: 10.4 months in 2023-24 versus 6.4 a decade earlier S9.
Our central 19 weeks sits within the published 16 to 24 week construction phase and below the 28 to 40 weeks one Brisbane source gives for volume builders, which probably counts calendar time including delays. Published whole-project times of about 10 to 12 months from approval are much longer than on-site construction because they include design, approvals, waiting for trades and weather.
Labour
Our central programme needs about 353 person-days on site. For the building trades covered by the Building and Construction (Residential) Award (279 person-days), the award wage floor alone comes to about $70,400. Plumbers, electricians and other trades covered by other awards (74 person-days) are not priced. That floor excludes superannuation, insurances, leave, supervision and subcontractor margin, so it is a lower bound, not a labour cost. We have not found published charge-out rates or labour hours per task, and crew sizes are our assumptions. Award minimum rates from 1 July 2026 (S8):
| Classification | Weekly hire, $ per hour |
|---|---|
| Trades assistant, labourer (level 1d) | $29.47 |
| Concrete finisher, steelfixer (level 2) | $30.03 |
| Carpenter, tiler, plasterer, roof fixer, painter, waterproofer (level 3; carpenter and tiler shown) | $31.95 |
6. Ten opportunities, ranked
Ranked by the addressable cost pool in the central case: the baseline cost of the elements each measure could change. Pools overlap, so they cannot be added, and a pool is what is at stake, not a saving. We have not estimated savings percentages because we have no verified data for them. The value of a week of programme is illustrative, about $1,875 in our earlier example, so saving eight weeks would be worth about $15,000 (our assumption).
| Opportunity | Addressable pool (central) | Elements | What would change | Evidence for savings |
|---|---|---|---|---|
| 1. Cut the number of finishing trades and passes | $105,100 | Internal walls and ceilings, Kitchen, bathrooms and finishes | Panels or linings that arrive finished, fewer plaster and paint passes, simpler wet area layouts and standard joinery modules. | Durra Panel one-wall comparison: manufacturer claim of about 7.1% lower cost and ten fewer hours (reported, not independently verified). No published installed data for other systems. Manufacturer claim |
| 2. Factory-made wall panels instead of stick framing | $67,700 | Structural framing, External walls and cladding, Insulation, Windows and external doors | Panelised timber walls with factory-fitted insulation and windows, assembled on site in days. | A prefabrication review reported to us found savings of up to 60% in time, 37% and 15.4% (reported, paper not read by us, so not used as a finding). Productivity Commission: housing construction productivity has fallen; detached houses took 10.4 months in 2023-24 versus 6.4 a decade earlier. Published benchmark |
| 3. Standardise joinery and fittings | $56,700 | Kitchen, bathrooms and finishes | Standard kitchen and wardrobe modules, fewer bespoke items, simple bathroom fit-outs. | Pekaj shows joinery as 5.5% of trade cost. No published savings figure. Our assumption |
| 4. Simplify services runs and reduce plant | $54,600 | Plumbing, electrical and air conditioning, External services and works inside the contract | Stack wet areas, shorten pipe and cable runs, passive design to reduce air conditioning load, one service trench. | Pekaj shows plumbing, electrical and air conditioning as 12.9% of trade cost. No published data on savings from layout. Our assumption |
| 5. Lighter or simpler foundations | $31,600 | Foundations and slab, Site preparation and earthworks | Optimised slab thickness and edge beams, void former choice, systems such as BIAX, matched to the site class. | Published QS rates $95 to $135 per m2 for waffle slabs (Melbourne, reported, not read by us). A feasibility study reported to us gave EPS pods at $13.06 per m2 and alternative void formers at $24.08 per m2. BIAX claims are company claims. Published benchmark |
| 6. Shorten the construction programme | $27,800 | Builder preliminaries | Fewer sequential trades, earlier ordering, factory work in parallel with site work, and fewer hold-ups from weather. | Illustrative arithmetic from our earlier published example (assumption). Productivity Commission data on slower build times. Our assumption |
| 7. Simplify roof form and reduce eaves | $17,600 | Roofing | The roof is 213.5 m2 in plan over a 173.4 m2 footprint (about 40 m2 of eaves). Trim overhangs where shading is not needed. | Roof areas come from our takeoff; unit rates are published benchmarks (S6). Published benchmark |
| 8. Lower-cost or integrated wall cladding | $17,600 | External walls and cladding | Compare brick veneer, fibre cement and wall systems that combine structure, insulation and cladding. Hemp block material rates reported to us run $90 to $365 per m2 of wall before installation. | Hemp prices are reported supplier rates, not read by us, and are material only. The brick veneer allocation here works out at about $185 per m2 of net wall (a derived figure). Published benchmark |
| 9. Reduce glazing area and standardise window sizes | $16,000 | Windows and external doors | Mallee has about 46 m2 of openings (31% of living area). Fewer, standard-size units, with the energy modelling re-run to check the effect. | Opening areas come from our takeoff. No published window price per m2 was found. Our assumption |
| 10. Fit the design to the site | $3,500 | Site preparation and earthworks | A level block, set-down slab and less cut and fill avoid the biggest swing items. | Published provisional sums range from $10,000 to $35,000 on ordinary sites and far more on steep ones (S1, S2, S13). Published benchmark |
7. What kind of evidence is each figure?
| Class | Meaning | Share of central total |
|---|---|---|
| Verified price | A specific current price we read at its source (a price list or quotation). None yet for the conventional baseline. | 0% |
| Published benchmark | A figure published by a builder, quantity surveyor, industry body or award, read by us through a page summary. It is not a quotation and may not match our reference building. | 69% |
| Manufacturer claim | A figure supplied by a product maker. Not independently verified. | 0% |
| Our assumption | A value chosen by us, with the reason stated. It is the weakest class and should be replaced first. | 31% |
Sources we used. Unless the table says otherwise we read them through page summaries from a fetch tool, not the original documents, and figures one source quotes from another (the AIQS index in S4, for example) are second-hand:
| ID | Source | Date | Class | How we read it | What we used it for |
|---|---|---|---|---|---|
| S1 | Newstart Homes: How much does it cost to build a house in Queensland | 1 October 2026 | Published benchmark | Page summary from the fetch tool, not the original document | Brisbane $1,500 to $1,800 per m2 base builder; provisional site works and connection ranges |
| S2 | Propertylens: Building a new home in Brisbane | Early 2026 (not stated) | Published benchmark | Page summary from the fetch tool, not the original document. The Brisbane mid-market range is a builder quote repeated by the site | Volume and mid-market $/m2; stage timelines; site cost examples |
| S3 | OJ Pippin: How much to build a house in Brisbane | 13 February 2026 | Published benchmark | Page summary from the fetch tool, not the original document | Broad $/m2 range; internally inconsistent upper figure |
| S4 | Pekaj Group: Melbourne construction costs 2026 | 4 April 2026 | Published benchmark | Page summary from the fetch tool, not the original document. Quotes the AIQS Building Cost Index (March 2026) figures, so those are second-hand: we have not seen AIQS itself | Trade-line and ANZSMM cost shares, margin, AIQS BCI cross-check; Melbourne, builder-published, not a Brisbane price |
| S5 | Yakka Labour: Concrete slab cost | 1 October 2026 | Published benchmark | Page summary from the fetch tool, not the original document | House slab $/m2 incl GST; engineering, soil test and termite extras |
| S6 | Yakka Labour: Colorbond roofing cost | 1 October 2026 | Published benchmark | Page summary from the fetch tool, not the original document | New roof $/m2 incl GST, Brisbane $65 to $105 |
| S7 | Rider Levett Bucknall: Australia Market Intelligence Update Q2 2026 | June quarter 2026 | Published benchmark | Page summary from the fetch tool, not the original document | Brisbane tender price forecasts and material price movements; no house $/m2 given |
| S8 | Master Builders WA: Building and Construction (Residential) Award 2020 wages, July 2026 | From 1 July 2026 | Published benchmark | Page summary from the fetch tool, not the original document | Award minimum hourly rates; the national award text itself was not read by us |
| S9 | Home Loan Experts: Stages of construction | Updated 18 September 2026 | Published benchmark | Page summary from the fetch tool, not the original document | Stage durations; ABS national average 11.5 months (via NHSAC, as reported) |
| S10 | Carlisle Homes: The 7 construction phases of a house | 28 January 2025 | Published benchmark | Page summary from the fetch tool, not the original document | 16 to 24 week construction phase; inspection points |
| S11 | Brighton Homes: How long does it take to build a house in Queensland | Not stated | Published benchmark | Page summary from the fetch tool, not the original document | Project home 6 to 12 months; delay causes |
| S12 | Business Queensland: Stages of a building inspection | Current page | Published benchmark | Page summary from the fetch tool, not the original document | Class 1a mandatory inspection stages: excavation, footings, slab, frame, final |
| S13 | Shore Building: Most expensive part of building a house | Reviewed 27 October 2026 | Published benchmark | Page summary from the fetch tool, not the original document | Sydney element shares and site work ranges, one builder's estimates |
| S14 | BMT Quantity Surveyors: Construction cost table | 2026 (no date given) | Published benchmark | Page summary from the fetch tool, not the original document | Brisbane 98 to 110% of Sydney; GFA definition; no dollar rates shown on the page |
| S15 | QBCC: Cementing your knowledge | 23 February 2022 | Published benchmark | Page summary from the fetch tool, not the original document | Curing guidance without a number of days |
We also reuse earlier findings that remain unread by us: the Pekaj waffle slab rates, a void former feasibility study and a prefabrication review, all reported by research partner, not read by us. The Durra Panel comparison is a manufacturer claim.
8. Uncertainties and questions for quotation
| Item | What to ask | What it affects | Who |
|---|---|---|---|
| No builder or quantity surveyor has priced the Mallee House | Ask two or three Brisbane volume and mid-market builders, or a quantity surveyor, for a priced estimate of the Mallee drawings on a standard Class M site, with the schedule of inclusions. | Replaces all benchmark allocations with measured prices | Ross to request |
| Benchmarks differ in what they include and whether GST is added | Confirm GST basis, what site works, preliminaries and margin each benchmark includes, and the date and floor area basis. | Moves the total by roughly 10% (GST) and more for site costs | Quotation |
| The element split is borrowed from a Melbourne two storey townhouse example | Ask a Brisbane builder for a trade-by-trade split of a single storey project home. | Changes every element line, not the total | Quotation |
| Floor area basis for cost per square metre | Confirm whether the quantity surveyor or builder includes the garage and the 30 m2 of pergola decks, and in which basis the benchmark rates are stated. | A 17% larger area basis (204 m2 instead of 174) lowers cost per m2 by about 15% | Quotation |
| Slab design is unknown | Obtain a soil test and a slab engineer's design for a typical SEQ block, with edge beams, reinforcement and concrete volume. | Foundation cost and curing time | Engineer |
| Slab curing period before framing | Ask the engineer and builder what minimum curing time they specify before loading the slab. | Programme, one to two weeks | Engineer and builder |
| Cladding and wall construction are not specified | Confirm the conventional wall type the builder would use (brick veneer or lightweight cladding) and the insulation R values required by the 7 star or higher energy design. | Walls and insulation lines | Builder |
| Window and door specification | Ask for a priced window and door schedule at the Mallee sizes, including glazing type and the supply lead time. | Windows line, which may exceed the benchmark | Supplier |
| Labour hours and charge-out rates | Ask builders for hours and crew sizes per trade and the rates actually charged. Award minimums exclude on-costs and subcontractor margin. | Labour requirements and savings potential | Builder |
| Trade durations and overlaps in the programme | Ask a builder to review the programme: durations, crew sizes, which trades overlap, and typical lost days in South East Queensland. | Programme total | Builder |
| Weather and supply allowances | Ask builders what delay allowance they price for wet weather, the Christmas shutdown and material lead times. | Programme high case | Builder |
| Escalation | Confirm what price date builders apply and the escalation clause. RLB forecasts Brisbane tender prices up 5.0% in 2026 and 7.0% a year from 2027 (a commercial index, not a house index). | Totals if building starts in 2027 | Builder |
| Insulation, finishes and fittings rates | Ask for installed rates (batts, plasterboard, paint, tiling, floor coverings) and standard kitchen and bathroom allowances. | Insulation, internal and fit-out lines | Supplier |
| Reported figures we have not read | Open the Pekaj waffle slab rates, the void former study and the prefabrication review, and confirm each. | Foundation and prefabrication opportunity evidence | Ross or Atlas |
9. The Mallee 8.5-star reference scenario
The baseline above is a generic conventional house priced from published benchmarks. The Mallee House as designed is not generic: it is an 8.5 star design with a specific make-up. We keep the generic baseline and describe the Mallee specification separately, so that nothing in the benchmark is silently changed to match it. This is the specification we read in the original Design Options and drawings:
| Element | Mallee 8.5 star specification | Source | How read |
|---|---|---|---|
| Internal partitions | 10 mm plasterboard on timber framing with R1.0 batts | Design Options pp 6 to 7 | Read by us in the original PDF |
| Ceiling | 10 mm plasterboard on timber framing with R4.0 batts | Design Options pp 6 to 7 | Read by us in the original PDF |
| External walls | Timber frame with R2.5 batts, sarking, battened air gap and 9 mm fibre cement, or brick veneer (two options) | Design Options pp 6 to 7 | Read by us in the original PDF |
| Windows | Single glazed timber frames, about half of the window area as glass louvres (drawing 11) | Design Options and drawing 11 | Read by us in the original PDF |
| Window area by type | About 23.9 m2 of windows: louvre about 11.8 m2, fixed glass about 12.1 m2 (nominal sizes from drawing 11, our sums) | Drawing 11 | Read by us in the original PDF |
| Openings in total | About 46 m2 of openings, 31% of the living floor area | Our takeoff | Our measurement |
Three of these differ from what the benchmark assumes. Single glazed timber windows with louvres are not the aluminium windows in the benchmark, and we have no published price for them. R4.0 ceiling and R2.5 wall batts are not the “standard” insulation of the benchmark either, and we found no published batt prices. The partition and ceiling lining is conventional, so the benchmark fits it. Rather than invent a price, we show how sensitive the central total is to the window element, as an illustration with multipliers of our own choosing:
| Window cost | Windows element | Central total, ex GST | Per m² GFA | Change |
|---|---|---|---|---|
| 1.0 times the aluminium window benchmark | $16,000 | $365,400 | $2,100 | $0 |
| 1.5 times the aluminium window benchmark | $24,000 | $375,000 | $2,155 | +$9,600 |
| 2.0 times the aluminium window benchmark | $32,000 | $384,600 | $2,210 | +$19,200 |
The multipliers are our assumption. They are not a finding that timber louvre windows cost 1.5 or 2.0 times as much. A window supplier’s quote for the drawing 11 schedule would replace them.
10. Reusing the model
The model lives in the project repository as a data file with a generator. To test an alternative, such as a different foundation, wall or panel system, supply a scenario file with that element’s low, central and high cost, its system and its evidence class. The generator then recomputes the total, cost per m² and programme beside this baseline. Programme durations can be changed the same way. Each new system carries its own evidence label, so verified prices and claims are never mixed.
This is preliminary. It will change when builders and quantity surveyors price the drawings. We would rather publish a transparent baseline now and improve it than wait for perfect information.